Finsbury Estate Landscaping Improvements
Estimated value
£210k
Awarded value
£210k
Suppliers
1
Lots
1
Published
02 May 2024
Description
This project aims to improve the accessibility of the central pathway and waste and recycling provision at Finsbury Estate. A key element of this scheme is to reconfigure the waste and recycling arrangement making it more pleasant and functional for residents without removing the convenience of its current location. This project is needed as the current bin area is not fit for purpose and does not provide the correct bin capacity required for the number of residents on the estate. Inadequacy of the current capacity has resulted in multiple complaints and bin collections needing to be scheduled daily to maintain an acceptable standard both visually and from a health and safety perspective.
Scope
- Reference
- 2324-0081
- Total value
- £209,503 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 01 Jan 2024 to 31 Mar 2024
- CPV classifications
- 45000000
- Particular suitability
- Small and medium-sized enterprises (SME)
Submission & procedure
- Submission deadline
- 20 Oct 2023, 11:00 am
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£210k
Award date
23 Nov 2023
Contract start
01 Jan 2024
Contract end
31 Mar 2024