CP7 Eastern Region Renewals and Minor Enhancements
Estimated value
£4.0bn
Awarded value
—
Suppliers
0
Lots
5
Published
07 Apr 2022
Description
Network Rail propose to procure renewals and minor enhancement adopting an integrated multi-discipline rail system approach that is flexible with a focus on productivity and passenger outcomes. Network Rail has set 5 strategic focus areas – a railway system approach; capabilities; productivity; collaborative behaviours; and sustainability. All these focus areas support the Agile Client Eastern (ACE) Capital Delivery operating model. Further information on the ACE operating model can be found within the Procurement Documents. Two Partnerships (North/South) will be created in the Eastern region. Key to their success will be aligned objectives and collaborative behaviours, where Network Rail will create competitive tension and adopt an incentivisation mechanism that will drive enhanced performance whilst fostering a culture of continuous improvement, quality driven outputs and delivering innovative solutions. The partners can undertake works and/or services in relation to the scope of their Lot and in addition undertake those works as part of Work Orders led by other partners. For example, the Structures, Geotechnics and Buildings partner can undertake the Structures, Geotechnics and Buildings works associated with a Signalling or OLE Works Order. In addition, where it provides value for money to do so for Network Rail, the partner may undertake works that are reasonably necessary to be supplied or installed contemporaneously with the Work Order. This could include but is not limited to the adjustment of Overhead Lines or track when undertaking a bridge replacement by a Lot 1 or 2 Structures, Geotechnics and Buildings partner. The Framework terms and conditions will provide NR with the flexibility to request partners to undertake CP7 work bank projects in both the North and South partnership regions. Network Rail is looking to appoint 14 construction partners to deliver the CP7 renewals and minor enhancement works across the Eastern Region. In addition, 5 secondary suppliers will also be appointed per Lot who sits outside the partnership. The partners will be appointed across 5 Lots as follows:- Lot 1 Structures, Geotechnics & Buildings (North): 3 partners plus 1 secondary supplier Lot 2 Structures, Geotechnics & Buildings (South): 3 partners plus 1 secondary supplier Lot 3 Signalling and Telecoms North & South: 4 partners (2 per partnership region) plus 1 secondary supplier Lot 4 Electrification & Power - Contact Systems North & South: 2 partners (1 per partnership region) plus 1 secondary supplier Lot 5 Electrification & Power - Distribution and Plant North & South: 2 partners (1 per partnership region) plus 1 secondary supplier The partners will be responsible for the design and construction works for the CP7 work bank for their respective Lot. The partners will be appointed via a Framework and a Partnering Agreement. The partners may also be asked to undertake emergency works and services. The Framework duration will be 5 years with an option to extend by a further 5 years with a 4-month mobilisation period and a further period to complete outstanding works. The contract is divided into 5 Lots. Tenders may be submitted for a maximum of 2 Lots. The estimated total value of the Framework will be within the range of £3,500,000,000 to £4,000,000,000 for the 10-year duration.
Scope
- Reference
- ocds-h6vhtk-030b8e
- Total value
- £4,000,000,000 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
The initial term of the framework will be 5 years (plus mobilisation period) with an option, subject to the successful supplier's performance during the initial term and on-going need by Network Rail to extend for a further period up to 5 years. The estimated total value of Lot 1 will be within the range of £750,000,000 to £850,000,000 for the 10-year duration.
- Main category
- works
- CPV classifications
- 4510000045200000452100004521332045213321452211124530000045234000452341154523411671311230452322104531540045315600
- Contract locations
- UK
Submission & procedure
- Submission deadline
- 13 May 2022, 11:00 am
- Submission address
- https://www.networkrail.bravosolution.co.uk/ ↗
- Procedure
- Competitive procedure with negotiation
Lots · 5 total
Divisions of the contract. Each lot can be awarded separately.
| Lot | Title | Est. value | Status |
|---|---|---|---|
| 1 | Structures, Geotechnics & Buildings (North) | £850.0m | active |
| 2 | Structures, Geotechnics & Buildings (South) | £850.0m | active |
| 3 | Signalling & Telecoms | £300.0m | active |
| 4 | Electrification & Power - Contact Systems | £480.0m | active |
| 5 | Electrification & Power – Distribution & Plant | £520.0m | active |