CRSTS Fitzwilliam Corridor Sustainable Transport Scheme

View buyer

Estimated value

£12.2m

Awarded value

£884k

Awarded 30 Aug 2023

Suppliers

1

Lots

1

1 awarded

Published

11 Sept 2024

Deadline 13 Nov 2023

Description

RMBC require a suitable contractor to design and build a sustainable transport corridor incorporating Fitzwilliam Road and St Anns Roundabout along with improvements to the adjacent Eastwood and Herringthorpe neighbourhood as follows: • The Fitzwilliam Road scheme will seek to introduce bus priority lanes and separated cycle lanes. • The St Anns roundabout is being redesigned to enhance pedestrian and cycle facilities. • Eastwood/Herringthorpe neighbourhood style improvements This is a 2 stage procurement via YORCIVIL major Works Framework Lot 1 for stage 1 Design/Pre-Construction Services, and stage 2 works/build. Stage 1 is expected to be completed within 12 months, with an option to extend into stage 2 works for a further 18 months at a total potential cost of £12,200,000

Scope

Reference
22-233
Total value
£12,200,000 excluding VAT
Commercial tool
Standalone contract
Contract dates
19 Feb 2024 to 11 Feb 2025
CPV classifications
45211360
Particular suitability
Small and medium-sized enterprises (SME)

Submission & procedure

Submission deadline
13 Nov 2023, 12:00 pm

Award details

Awarded supplier(s), contract period and value as published in the award notice.

Awarded value

£884k

Award date

30 Aug 2023

Contract start

19 Feb 2024

Contract end

11 Feb 2025