Storage Solutions - Gamston
Estimated value
—
Awarded value
£17k
Suppliers
1
Lots
1
Published
15 May 2024
Description
Design, supply & install storage solutions at our Gamston depot, using Palletstor Racking System (or equivalent to clip into the existing system). To include safe removal and disposal of current tack welded angle iron to frames and all existing shelving/racking, to allow suitable access to construct new racking and shelving.\r \r The pallet racking (suitable for loading pallets with a forklift) should hold 2500kg per shelf. The Longspan shelving (or equivalent that clips into the existing system) should be capable of supporting 500kg per shelf.\r \r Images of the existing racking to be dismantled are attached. The amount of racking to dismantle is broadly similar to the amount Via need replacing. Also note the shelving to be removed in last image is welded to the portal frame of the warehouse, so consideration needs to be given for dismantling this racking. A site visit is recommended.\r \r Site visits are to be completed by CoB 24th April 2024, please contact Andy Ramsden / Dale Holmes to arrange a site visit andy.ramsden@viaem.co.uk and dale.holmes@viaem.co.uk.\r \r Price breakdowns are required in 3 elements, therefore please submit your pricing as follows: -\r 1) Supply & installation of Racking\r 2) Supply & installation of Shelving\r 3) Dismantle & remove existing shelving
Scope
- Reference
- VIA001-DN718678-16055092
- Commercial tool
- Standalone contract
- Contract dates
- 06 May 2024 to 26 Jun 2025
- CPV classifications
- 45213220 45213221
- Particular suitability
- Small and medium-sized enterprises (SME)
Submission & procedure
- Submission deadline
- 29 Apr 2024, 10:00 am
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£17k
Award date
14 May 2024
Contract start
06 May 2024
Contract end
26 Jun 2025