Mersey Gateway Bridege Traffic Modelling

Department for TransportcontractContracts FinderRef PPRO 04/37/41complete
View buyer

Estimated value

£64k

Awarded value

£64k

Awarded 11 Jan 2016

Suppliers

1

Lots

1

1 awarded

Published

14 Jan 2016

Deadline 08 Dec 2015

Description

The Mersey Gateway Bridge is a large suspension bridge under construction across the River Mersey in England by Halton Borough Council. It is to be funded through tolls plus additional payments provided by the UK Government. The Full Business Case submitted to the Department in January 2014 included a Local User Discount Scheme (LUDS). In July 2014, the Chancellor announced that the LUDS would be extended from 300 trips/year to an unlimited number and be available to all Halton residents. Subsequently in July 2015, the Chancellor also stated that “The government is looking at extending Mersey Gateway bridge toll discounts to residents of Chester West & Chester and Warrington, with final decisions to be made in early 2016.” The proposed Scope of Work is intended to update the underlying traffic modelling to allow an estimate of the financial and economic implications of the committed (within Halton BC area) and further possible extensions (to adjacent LA areas) to the LUDS.

Scope

Reference
PPRO 04/37/41
Total value
£64,250 excluding VAT
Commercial tool
Standalone contract
Contract dates
11 Jan 2016 to 30 Mar 2016
CPV classifications
73000000

Submission & procedure

Submission deadline
08 Dec 2015, 12:00 am

Award details

Awarded supplier(s), contract period and value as published in the award notice.

Awarded value

£64k

Award date

11 Jan 2016

Contract start

11 Jan 2016

Contract end

30 Mar 2016