BATTYEFORD CE (VC) PRIMARY SCHOOL - BOILER PLANT REPLACEMENT
Estimated value
£185k
Awarded value
£100k
Awarded 03 Aug 2025
Suppliers
1
Lots
1
1 awarded
Published
07 Aug 2025
Deadline 23 Jul 2025
Description
The removal of the existing mechanical services and the installation of the new gas fired boilers, flue system, pressurisation unit, heating pumps and circulators, BMS and controls, steel pipework, copper pipework, fittings, electrical works, builders work and asbestos removal. The work will be done in holidays and extend into term time while the school is operational. The contractor is expected to temporary wire the hot water for the start of the school.
Scope
- Reference
- 20250807113022-104104
- Total value
- £185,292 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 10 Aug 2025 to 09 Oct 2025
- CPV classifications
- 45350000 71333000 71334000
Submission & procedure
- Submission deadline
- 23 Jul 2025, 12:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£100k
Award date
03 Aug 2025
Contract start
10 Aug 2025
Contract end
09 Oct 2025