BBV Sublot 1B Tunnel Grout Treatment

Balfour Beatty VINCI JV HS2contractContracts FinderRef C4N99370407SME suitableclosed
View buyer

Estimated value

£2.5m

Awarded value

Suppliers

0

Lots

1

0 awarded

Published

08 Sept 2025

Deadline 15 Sept 2025

Description

"Ground Treatment " The SC (Subcontractor) will assess the findings of the probe hole investigation and will develop the grout treatment strategy to be followed with a scope to minimize any excess water ingress during CP excavation and improve the ground stability. Grouting operations will include stage permeation grouting on max 1m steps, with the use of packers. Subcontractor based on ground and ground-water conditions as revealed from ground investigation (probe holes) shall develop the grouting strategy. The strategy will include as a minimum but not exclusively the following: • A grouting pattern of primary and secondary on the periphery of CP profile • Drilling diameter, orientation, and lengths of each grouting hole • Bottom-up grouting stages with the use of packers. The grouting stages should not exceed the length of 1m. • In case required (unstable ground) Subcontractor may need to make use of a tube a manchette TAM (sleeve pipes) system to perform the grouting. In this case the strategy should be developed accordingly. • Mix design(s) of the grout injection • Max Pressure and max Volume criteria for stopping each grouting stage • Tertiary drilling holes in case primary and secondary do not reach the target criteria. • As built records grouting locations lengths stages grout consumptions and max pressure. "

Scope

Reference
C4N99370407
Total value
£2,500,000 excluding VAT
Commercial tool
Standalone contract
Contract dates
20 Nov 2026 to 22 Jan 2027
CPV classifications
44831400 45262340
Particular suitability
Small and medium-sized enterprises (SME)

Submission & procedure

Submission deadline