Havant Thicket Reservoir Project - Main Works Pipeline
Estimated value
£41.0m
Awarded value
£41.0m
Suppliers
1
Lots
1
Published
02 Sept 2022
Description
This represents a flagship project to construct the first new strategic water resource, and corresponding pipeline, in the South East for decades. Construction work is anticipated to start on the Havant Thicket Reservoir Project (the "Project") in 2024, for completion by 2029. The Project is the product of collaborative regional water planning particularly between Portsmouth Water and Southern Water, and forms a key step in increasing water resilience in the South East. The procurement of the main works contractor for pipeline construction works was carried out together with the procurement of the framework agreement for wider design services, together advertised in FTS Contract Notice 2021/S 000-000072. However, this award notice relates only to the award of the main pipeline works contract. It is anticipated that the framework agreement will be the subject of a separate award notice once the framework agreement has been completed.
Scope
- Reference
- BIP718362377
- Total value
- £41,014,620 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 05 Sept 2022 to 30 Oct 2028
- CPV classifications
- 45240000
Submission & procedure
- Submission deadline
- 03 Aug 2022, 11:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£41.0m
Award date
03 Aug 2022
Contract start
05 Sept 2022
Contract end
30 Oct 2028