The project involves replacing the main heating boilers, kitchen hot water heater and all associated equipment including flues, pumps, gas safety systems, pipework valves (within the plantrooms). A new mechanical control panel shall also be provided in the main boiler room. Final start on site dates to be agreed but the aim is to complete all works before July.