Ynysarwed Mine Water Treatment Scheme upgrade to High Density Sludge Treatment Plant Design and Build

The Coal AuthoritycontractContracts FinderRef CA18/4973SME suitablecomplete
View buyer

Estimated value

£4.7m

Awarded value

£4.7m

Awarded 26 Nov 2021

Suppliers

1

Lots

1

1 awarded

Published

28 Feb 2022

Deadline 17 Sept 2021

Description

Specialist contractor to undertake the design, construction and commissioning of a new high-density sludge treatment plant and decommissioning of the existing treatment plant. • The project objectives; • Replace the existing Treatment Plant with a High Density Sludge (HDS) plant; • Improve the scheme from an operational, environmental and health and safety perspective; • Improve the longevity and resilience of the scheme; • Provide efficiencies with improved chemical dosing and other controls; • Reduce operational costs; • Assess, record and reduce the carbon emissions associated with the life of the scheme; • Identify cost efficiencies; • Reduce risk of pollution of the River Neath and the Neath Canal; • Comply with the existing discharge consents; • Minimise the downtime of the existing scheme during construction; • Develop plans for the assessment, measurement, and continual improvement of waste management, sustainability and carbon impact for the construction, operation and decommissioning of the scheme.

Scope

Reference
CA18/4973
Total value
£4,688,222 excluding VAT
Commercial tool
Standalone contract
Contract dates
23 Dec 2021 to 29 Jul 2023
CPV classifications
45000000
Particular suitability
Small and medium-sized enterprises (SME)

Submission & procedure

Submission deadline
17 Sept 2021, 3:00 pm

Award details

Awarded supplier(s), contract period and value as published in the award notice.

Awarded value

£4.7m

Award date

26 Nov 2021

Contract start

23 Dec 2021

Contract end