S30026 Impacts of AVs on National Highways Operations
Estimated value
£227k
Awarded value
£227k
Suppliers
1
Lots
1
Published
09 Dec 2025
Description
Automated Vehicles will enable safer and more efficient journeys on the road network, however the introduction of AVs on to the SRN will also have impacts on National Highways Business as Usual Operations. The project will look at all aspects of how NH should interact with AVs on our network (for example: recovery procedures, AV fail safes impacts on SRN, ERA interaction, TOS interaction, traffic management requirements, other road user interaction, ROC interaction, Incident liability).
Scope
- Reference
- tender_505765/1538211
- Total value
- £226,851.29 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 02 Dec 2025 to 31 Dec 2027
- CPV classifications
- 73220000
- Particular suitability
- Small and medium-sized enterprises (SME)
Submission & procedure
- Submission deadline
- 13 Oct 2025, 6:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£227k
Award date
02 Dec 2025
Contract start
02 Dec 2025
Contract end
31 Dec 2027
Awarded suppliers· 1 supplier
Awarded 02 Dec 2025 · Contract period 02 Dec 2025 — 31 Dec 2027
Other contracts from National Highways
Full notice and award history for this contracting authority is on the buyer profile.
Other contracts awarded to WSP UK Ltd - SPaTS 1· 10
Cross-buyer view of this supplier's public-sector wins.
| Title | Type | Value | Published |
|---|---|---|---|
| S30098 Strategic Charging Infrastructure (SCI) technical partner | contract | £1.2m | 16 Jun 2026 |
| S30085 Consents on the M6 Toll Road from 2026 onwards | contract | £300k | 23 Apr 2026 |
| S30018 Development of new Lead Safety Indicators analysis testing and validation | contract | £100k | 26 Sept 2025 |
| S30020 Road Marking Certification Site | contract | £88k | 26 Sept 2025 |
| T0661 Technical Standards Implementation, Governance improvements and benefit realisation | contract | £219k | 08 Jul 2025 |
| T0665 Requirements and Advice for DHSR and Targeted Enhancements for APTR | contract | £349k | 04 Jun 2025 |
| T0652 Technical support for keeping the DMRB and MCHW up to date | contract | £720k | 23 Apr 2025 |
| T0648 Strategic consultancy to develop a renewable electricity procurement and generation strategy with power purchase agreements | contract | £150k | 28 Mar 2025 |
| T0643 Technical Support for Lands Claim | contract | £116k | 11 Feb 2025 |
| T0629 The effect of Climate Change on bridge design | contract | £135k | 15 Jan 2025 |