Radbourne Unit WC & Shower room refurbishments
Estimated value
£75k
Awarded value
£92k
Suppliers
1
Lots
1
Published
26 Nov 2018
Description
Expression of Interest to be considered for tender list - Based on the Royal Derby Hospital site, the Radbourne Unit is the Derbyshire Healthcare NHS Foundation Trust's main inpatient service for residents with acute mental health needs. The works will involve the full refurbishment of existing male & female WC facilities within the main reception area, full refurbishment of shower room & WC on the Beeches Mother & Baby unit, full refurbishment to shower rooms both male & female on wards 35 & 36. The ward and Unit will remain fully operational 24/7 during the works programme and tenderers will have to provide evidence of experience of working in a mental health hospital. Working hours may be limited to between the hours of 9.00am - 5.00pm and other working restrictions will be applied whilst ECT therapies are carried out each Monday and Thursday. No lone working of any type will be allowed. All works must be completed before 31 March 2019 and the successful contractor must submit a programme for approval. The Trust's Capital Team has a list of preferred suppliers who are experienced/specialists in the mental health environment and these suppliers will be named for doors, vision panels, glazing and building services including the staff attack alarm system and fire alarm system works.
Scope
- Reference
- 18046 Radbourne Unit WC & Shower room refurbishments
- Total value
- £75,000 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 05 Nov 2018 to 07 Dec 2018
- CPV classifications
- 45000000
- Particular suitability
- Small and medium-sized enterprises (SME)
Submission & procedure
- Submission deadline
- 09 Oct 2018, 11:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£92k
Award date
12 Nov 2018
Contract start
05 Nov 2018
Contract end