A9 Dualling: Pitlochry to Killiecrankie project

Transport ScotlandcontractFind a TenderRef ocds-h6vhtk-0509e332014L0024closed for bids
View buyer

Estimated value

£205.0m

works

Awarded value

Suppliers

0

Lots

1

0 awarded

Published

24 Jul 2025

Deadline 04 Sept 2025

Description

The Scope involves the dualling of approximately four miles (6.4km) of existing single carriageway on the A9 trunk road between Pitlochry and Killiecrankie. This consists of approximately 4km of online widening and approximately 2km of offline construction. The new/upgraded carriageway will be to Dual 2 lane All-purpose roads Sub-category c (D2APc) standard, in accordance with ‘CD 109 Highway Link Design’ within the UK Design Manual for Roads and Bridges. The project also includes (but is not limited to) construction of two grade separated junctions, construction of two left-in left-out junctions, construction of two major underbridges, demolition and replacement of three existing underbridges, an extension of one existing rail underbridge and construction of one new rail underbridge, provision of five other new underbridges/underpasses, six new retaining walls and fifteen culverts. Additionally, the project involves maintenance works at the existing Tummel underbridge, provision of traffic management, earthworks, road restraint systems, accommodation works, service diversions, fencing, signage, landscaping and environmental mitigation.

Scope

Reference
TS/MP/WKS/2025/01
Total value
£205,000,000 excluding VAT
Commercial tool
Standalone contract
Main category
works
CPV classifications
45111000
45221220
45221111
45221112
45233120
45233124
45233125
45233161
45233162
45233224
45233226
45233290
45262640
45233222
45112000
45112730
45233128
45233280
45246200
45316210
45454100
50230000
45316110
Contract locations
Scotland

Award criteria

Criteria the buyer will use to evaluate bids.

NameDescriptionTypeWeighting
Including approach to delivery & management, technical aspects, construction, commercial, risk and sustainability aspects of the project.50quality
Further information on scoring of the prices can be found in the Supplementary Information Document.50cost

Submission & procedure

Submission deadline
04 Sept 2025, 11:00 am
Submission address
http://www.publiccontractsscotland.gov.uk
Procedure
Competitive dialogue