GSK External Repairs & Decorations - AWARD
Estimated value
—
Awarded value
—
Suppliers
1
Lots
1
Published
08 Jun 2023
Description
This is an Invitation to Tender (ITT) with information, instructions and guidance provided in this document. Tender submission (consisting of the completion of the Technical Response, and Commercial response documents) should be completed and returned by all Tenderers who wish to bid for the contract. Please note, throughout the Tender documentation the University of Nottingham will be referred to as 'UoN' The UoN requests tenders from sufficiently experienced and qualified suppliers to establish a contract for the provision of external repairs and decorations to the GSK Carbon Neutral Laboratory at 6 Triumph Road, Jubilee Campus, Nottingham, NG7 2GA.
Scope
- Reference
- IT-55-1270-1922/ITTC/LH - AWARD
- Commercial tool
- Standalone contract
- Contract dates
- 17 Apr 2023 to 30 Sept 2023
- CPV classifications
- 45300000
Submission & procedure
- Submission deadline
- 25 Jan 2023, 8:50 am
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
—
Award date
07 Jun 2023
Contract start
17 Apr 2023
Contract end
30 Sept 2023
Awarded suppliers· 1 supplier
Awarded 07 Jun 2023 · Contract period 17 Apr 2023 — 30 Sept 2023
Other contracts from UNIVERSITY OF NOTTINGHAM (THE)
Full notice and award history for this contracting authority is on the buyer profile.
Other contracts awarded to Hilton Bodill Construction Ltd· 10
Cross-buyer view of this supplier's public-sector wins.
| Title | Type | Value | Published |
|---|---|---|---|
| 2113 FC16 RB - Re-roofing High Level Flat Roofs at Nightingale Hall for the University of Nottingham - AWARD | contract | — | 19 Nov 2024 |
| 2113 FC15 RB Alteration and Refurbishment of Laboratory LG56 within the Brain and Body Centre - AWARD | contract | — | 01 Nov 2024 |
| 2113 - FC04 - SB - Boiler Works - Sir Clive Grainger Building (Rutland and Sherwood Works Plan) - AWARD | contract | £1.1m | 31 Jul 2024 |
| 2113 - FC02 - SB - Boiler M+E Work - Portland Building (Rutland and Sherwood Works Plan) - AWARD | contract | £669k | 31 Jul 2024 |
| LASS Replacement Windows & Installation - AWARD | contract | £1.3m | 15 Dec 2023 |
| Clinical Sciences Building, City Hospital Campus - Minor Works - AWARD | contract | £121k | 19 Oct 2023 |
| The Firs Building - New Boiler Installation at Sutton Bonnington - AWARD | contract | £458k | 13 Jul 2023 |
| Wolfson Building B Floor Refurbishment - AWARD | contract | £278k | 13 Jul 2023 |
| Pope Building - UP - Office Refurbs - AWARD | contract | £60k | 31 May 2023 |
| Lenton Firs Head of Department Move | contract | £47k | 17 May 2023 |