Gilmour Section House Net Zero Phase 2 - Pipework Adaptions
Estimated value
£452k
Awarded value
£452k
Suppliers
1
Lots
1
Published
12 Nov 2025
Description
Modify existing LTHW PHEs. Install ASHP circulating pumps and pipework with buffer vessels, pipework insulation, vertical distribution, leak detection, and immersion heater to one buffer vessel. Install LTHW circulating pumps and distribution insulated pipework with energy meters on primary and secondary side. Energy meter for cold water fill for PU. Hot water twin pump sets and secondary pump, boiler circulation pump, cold water supply and a complete pipework system installation in the basement. Heat pump accessories with trace heating for external pipework. Reroute vent pipe on roof from the ASHP enclosure. HWS secondary pump and pipework with semi-instantaneous DHW calorifiers with associated PHE, pumps and electric immersion heaters.
Scope
- Reference
- 2413
- Total value
- £452,471.95 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 21 Oct 2025 to 11 Jun 2026
- CPV classifications
- 45000000
- Particular suitability
- Small and medium-sized enterprises (SME)
Submission & procedure
- Submission deadline
- 21 Oct 2025, 4:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£452k
Award date
20 Oct 2025
Contract start
21 Oct 2025
Contract end
11 Jun 2026