Harwell Bldg 462 Vent I/O
Estimated value
£180k
Awarded value
£134k
Suppliers
1
Lots
1
Published
01 Mar 2020
Description
Upgrading of Building B462 ventilation control systems to replace imminent obsolescent Sattcom I/O to include: 1) Design of solution. 2) Supply of hardware, see section below. 3) Creation of factory acceptance and commissioning tests to satisfaction of Magnox PM 4) Factory testing to satisfaction of Magnox PM 5) Supply of Method statements and Risk Assessments to satisfaction of Magnox safety department. 6) Installation of ABB S800 compatible I/O hardware to replace Sattcon I/O hardware leaving field wiring unchanged as much as possible. 7) Installation of any additional trunking, cabinets etc. as required by the solution. 8) Relocation of the PLC into a cabinet along with the I/O. 9) Update I/O addressing within PLC leaving application program unchanged. 10) Update Control Builder to latest version with associated media and licences. 11) Installation to be performed in such a way as to minimise downtime of the building ventilation system. 12) Commissioning to ensure operation of PLC is unchanged by upgrade to satisfaction of Magnox PM 13) Supply of drawings of physical and electrical installation as AutoCAD drawings on Magnox templates.
Scope
- Reference
- 20200301123050-3510
- Total value
- £180,000 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 24 Feb 2020 to 02 Jul 2020
- CPV classifications
- 31712113 51110000
- Particular suitability
- Small and medium-sized enterprises (SME)
Submission & procedure
- Submission deadline
- 18 Nov 2019, 12:00 am
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£134k
Award date
17 Feb 2020
Contract start
24 Feb 2020
Contract end
02 Jul 2020