DENBY DALE F & N SCHOOL - BOILER PLANT REPLACEMENT

Kirklees CouncilcontractContracts FinderRef 20221028123917-104104complete
View buyer

Estimated value

£135k

Awarded value

£111k

Awarded 18 Oct 2022

Suppliers

1

Lots

1

1 awarded

Published

28 Oct 2022

Deadline 10 Oct 2022

Description

The removal of the existing mechanical services and the installation of the new gas fired boilers,flue system, pressurisation unit, heating pumps and circulators, hot water calorifier, BMS and controls, steel pipework, copper pipework, fittings, electrical works, builders work and asbestos removal. The work will be done in term time while the school is operational therefore the contractor will be required to collect and use a mobile boiler unit (provided by Kirklees) to maintain heating and hot water during the works

Scope

Reference
20221028123917-104104
Total value
£134,762 excluding VAT
Commercial tool
Standalone contract
Contract dates
23 Oct 2022 to 19 Dec 2022
CPV classifications
42160000 45331110

Submission & procedure

Submission deadline
10 Oct 2022, 12:00 pm

Award details

Awarded supplier(s), contract period and value as published in the award notice.

Awarded value

£111k

Award date

18 Oct 2022

Contract start

23 Oct 2022

Contract end