Torness to Hawthorn Pit HVDC Link
Estimated value
—
Awarded value
—
Suppliers
3
Lots
2
Published
17 May 2024
Description
National Grid Electricity Transmission PLC (NGET) and SP Transmission PLC (SPTN) (the "Employers") are jointly developing a HVDC link between Torness, Scotland and Hawthorn Pit, England (the "HVDC Link"). This notice concerns the award of one or more Engineering, Procurement & Construction (EPC) contracts for the detailed design, engineering, procurement, manufacture, installation, construction, testing, commissioning, spares provision, operational hand-over and maintenance of the HVDC Link between Scotland and England.
Scope
- Reference
- ocds-h6vhtk-031223
- Commercial tool
- Standalone contract
- Main category
- works
- CPV classifications
- 3120000031321300452314004531431031321500
- Contract locations
- UK
Submission & procedure
- Procedure
- Negotiated procedure with prior call for competition
Award details· 2 awards
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
—
Award date
—
Contract start
—
Contract end
—
Lots · 2 total
Divisions of the contract. Each lot can be awarded separately.
| Lot | Title | Est. value | Status |
|---|---|---|---|
| 1 | EPC of HVDC Voltage Source Commutated (VSC) converter stations at both Torness & Hawthorn Pit and HVAC underground cable at Hawthorn Pit between Converter Station and Point of Common Connection (PCC) | £444.0m | cancelled |
| 2 | EPC of HVDC submarine and underground cable between converter stations (Torness & Hawthorn Pit) inc. HVAC underground cable at Torness between converter station & Point of Common Connection (PCC). | £480.0m | cancelled |