Workington Gateway

Cumberland CouncilcontractContracts FinderRef CC001-DN739098-68697919SME suitablecomplete
View buyer

Estimated value

£3.8m

Awarded value

£224k

Awarded 22 Nov 2024

Suppliers

1

Lots

1

1 awarded

Published

09 Dec 2024

Deadline 11 Oct 2024

Description

The Project forms part of the wider Workington Gateway programme, which is made up of the following elements:\r 1. Ramsay Brow junction (A66/A596) improvement to improve access to strategic employment sites, including the Port of Workington.\r 2. Road widening of Hall Brow (A596) to improve access to strategic employment sites, including the Port of Workington.\r 3. Local active travel network improvements and enhanced public realm, including a new LTN1/20 compliant east-west cycle route through Hall Park running parallel and complementary to the A66, supporting proposals in the Local Cycling and Walking Infrastructure Plan (LCWIP).\r 4. Enhancement of the cultural offer and visitor experience within Hall Park, including creation of a Social Enterprise Centre within the Walled Garden, and feature lighting of Workington Hall.\r \r \r This Project will generally comprise:\r • Realignment and widening of the A66 Ramsay Brow/ A596 junction, allowing HGV movement from the A66 to the employment and distribution sites north of Workington.\r o A pocket park to replace the existing Henry's pub site with improved public realm, seating and a landscaped area.\r o New toucan crossings on the eastern and southern arms of the junction.\r o New cycle infrastructure along the A596 eastern footway between the A66 and Ladies Walk.\r o Widening of the A66 Ramsay Brow southern footway to achieve minimum 2m width throughout.\r • Widening of the A596 Hall Brow, allowing HGV movement from the A66 to the employment and distribution sites north of Workington.\r o Formal permit-holder only parking for the Hall Brow residents.\r o Relocated existing park boundary wall to accommodate carriageway widening.\r o New parallel Toucan crossing for pedestrians and cyclists across the A596, connecting Black Path to the park.\r \r The Project will be delivered in two stages:\r Stage 1: Design and production of Stage 2 Works Information: Administered under NEC3 ECC Option A.\r Stage 2: Construction: Administered under a separate NEC3 ECC Option A.\r There will be a decision hold-point between Stage 1 and Stage 2 where the Employer may choose to proceed, or not to proceed to Stage 2.\r \r Suppliers wishing to express an interest and obtain access to the tender documents should go to www.the-chest.org.uk and click on current opportunities from the navigation area on the left of the screen. On the next screen enter the contract Reference DN739098 in the box labelled 'contains' then click search. Click on the Blue link for the contract title to view the opportunity. \r To express an interest you will need to login. If you are not already registered on the www.the-chest.org.uk you will need to return to the home page and click on Register. Register free link in the navigation area on the left of the screen. Registration is free of charge and your username and password will be emailed to you.\r

Scope

Reference
CC001-DN739098-68697919
Total value
£3,790,000 excluding VAT
Commercial tool
Standalone contract
Contract dates
20 Oct 2025 to 30 Jan 2026
CPV classifications
45000000
Particular suitability
Small and medium-sized enterprises (SME)

Submission & procedure

Submission deadline
11 Oct 2024, 10:59 pm

Award details

Awarded supplier(s), contract period and value as published in the award notice.

Awarded value

£224k

Award date

22 Nov 2024

Contract start

20 Oct 2025

Contract end

30 Jan 2026