CHP BMS Controls Optimisation
The Mersey Docks and Harbour CompanycontractFind a Tender ↗Ref ocds-h6vhtk-066ea1Procurement Act 2023active
Estimated value
—
Awarded value
—
Suppliers
1
Lots
1
1 awarded
Published
19 Mar 2026
Description
Carry out the CHP controls optimisation works within the existing BMS system. ● Reinstate the "Load Follow" PLC functionality to allow the CHP to modulate based on the site actual load. ● Control optimisation to balance the CHP and Solar systems ensuring priority is given to the CHP and its minimum turndown ● Energy Markets management system to improve revenue generation through smart controls and grid management
Scope
- Reference
- ocds-h6vhtk-066ea1
- Commercial tool
- Standalone contract
Submission & procedure
- Procedure
- Below threshold - unknown
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
—
Award date
—
Contract start
—
Contract end
—
Awarded to
VE
CH 02481991