Resurfacing of the Main Deck of the Tamar Bridge, including the north and south cantilever lanes.

Cornwall CouncilcontractContracts FinderRef CORNWALL001-DN422865-80620787SME suitablecomplete
View buyer

Estimated value

£5.3m

Awarded value

£3.8m

Awarded 16 Feb 2021

Suppliers

1

Lots

1

1 awarded

Published

25 Feb 2021

Deadline 30 Jul 2020

Description

Resurfacing of the Main Deck of the Tamar Bridge, including the north and south cantilever lanes. The successfully appointed Contractor will also be required to safely remove the existing installed series of illuminated lane studs and ensure resurfacing work is completed to the agreed programme, to allow for prompt installation of the replacement studs by the separately appointed supplier, as a key part of the overall resurfacing project. There is also the potential scope to include ancillary expansion joint replacement and resurfacing of the Toll Plaza Area. The value of the Works is estimated to be within the range of £4.5M to £5.3M GBP. The work is anticipated to take place over a period of up to 6 months, anticipated to commence from April 2021. The resurfacing overall is concerned with implementing Stage 2 of the current resurfacing strategy and follows on from the resurfacing Stage 1 of the Plymouth side span in 2011. The stage 1 works just replaced the worst section that had failed prematurely, due to onerous loading conditions. Stage 2 of the resurfacing strategy, which includes the main deck centre span and the Saltash side span and north and south cantilever lanes, was based on a policy of lifetime maximisation of the existing surfacing system until such a point when noticeable and problematic degradation commenced. At the time it was anticipated that the remaining areas would achieve their anticipated design life span in excess of twelve years and at the then anticipated levels of degradation was expected to last for another 3-7 years (2014-2018). It is now the point where the maximum life has been extracted from the remaining surfacing and replacement is required, commencing in Spring 2021.

Scope

Reference
CORNWALL001-DN422865-80620787
Total value
£5,300,000 excluding VAT
Commercial tool
Standalone contract
Contract dates
31 Mar 2021 to 29 Sept 2021
CPV classifications
45233223 45233251
Particular suitability
Small and medium-sized enterprises (SME)

Submission & procedure

Submission deadline
30 Jul 2020, 12:00 am

Award details

Awarded supplier(s), contract period and value as published in the award notice.

Awarded value

£3.8m

Award date

16 Feb 2021

Contract start

31 Mar 2021

Contract end

29 Sept 2021

Awarded to