Church Lane Diversion Works
Estimated value
£40k
Awarded value
£38k
Awarded 25 Sept 2017
Suppliers
1
Lots
1
1 awarded
Published
26 Sept 2017
Deadline 24 Sept 2017
Description
Installation of new highway drain to create a diversion from existing watercourse, including the installation of 5 new road gullies and 2 new manholes.
Scope
- Reference
- WIGN001-DN297499-96417770
- Total value
- £40,000 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 22 Oct 2017 to 03 Nov 2017
- CPV classifications
- 65100000
Submission & procedure
- Submission deadline
- 24 Sept 2017, 11:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£38k
Award date
25 Sept 2017
Contract start
22 Oct 2017
Contract end
03 Nov 2017
Awarded to