Design & Construction of a Solar Canopy for the GULCS Project
Estimated value
£200k
Awarded value
£200k
Suppliers
1
Lots
1
Published
09 Sept 2020
Description
South Gloucestershire is installing a flagship Electric Vehicle Go Ultra Low Charging Station (GULCS). The GULCS will provide up to eight rapid charging bays and will be located at the Bristol and Bath Science Park on Feynman Way, South Gloucestershire.This contract is for the design, manufacture, installation and maintenance of a solar canopy for the GULCS. The appointed contractor shall demonstrate experience of designing, planning, scheduling, constructing and maintaining solar canopies, with good experience/knowledge of working with local authorities.
Scope
- Reference
- SGLOS001-DN428767-73404875
- Total value
- £200,000 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 16 Jan 2020 to 27 Aug 2020
- CPV classifications
- 09330000 45261000
- Particular suitability
- Small and medium-sized enterprises (SME)Voluntary, community and social enterprises (VCSE)
Submission & procedure
- Submission deadline
- 12 Sept 2019, 11:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£200k
Award date
20 Oct 2019
Contract start
16 Jan 2020
Contract end
27 Aug 2020