Upgrade to existing Natural Gas Roller Hearth Tile Kiln to fire on 100% Hydrogen
Estimated value
£250k
Awarded value
£258k
Suppliers
1
Lots
1
Published
01 Dec 2023
Description
The design, supply, and installation of modifications to our existing Natural Gas Roller Hearth Tile Kiln. Our organisation intends to transition the kiln to operate on 100% hydrogen, whist retaining the existing natural gas combustion system and ensuring its safe and efficient operation. The kiln therefore requires the parallel installation of 100% hydrogen rated burners. The existing asset has been used in the past to investigate the use of Flash Sintering of ceramic tiles is used as a laboratory/research platform for the ceramic tile sector and as such the final design should not compromise the asset's current capabilities, which are; 1170⁰C peak operating temperature, product setting volume to be unchanged. The existing asset was recommissioned in January 2023 after several years of being offline. It has a fully integrated SCADA control system that manages the kiln automation and combustion control current operation. Interested parties are to contact James Till at james.till@uk.lucideon.com to register their interest and will be provided a copy of the ITT and a PQQ for completion. If you have any questions or comments in relation to this tender, they must be submitted to james.till@uk.lucideon.com Completed tenders must be submitted to james.till@uk.lucideon.com or in writing to our head office. Closing date for receipt of tenders: 6th October 2023 at 12:00 (UK time).
Scope
- Reference
- LUC0012
- Total value
- £250,000 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 30 Nov 2023 to 02 May 2024
- CPV classifications
- 42300000
- Particular suitability
- Small and medium-sized enterprises (SME)
Submission & procedure
- Submission deadline
- 06 Oct 2023, 11:00 am
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£258k
Award date
30 Nov 2023
Contract start
30 Nov 2023
Contract end
02 May 2024
Awarded suppliers· 1 supplier
Awarded 30 Nov 2023 · Contract period 30 Nov 2023 — 02 May 2024