Multi Disciplinary Design Team

ST OSYTH PRIORY & PARISH TRUSTcontractContracts FinderRef St. Osyth Priory and Parish procurement 2complete
View buyer

Estimated value

£227k

Awarded value

£138k

Awarded 17 Aug 2025

Suppliers

1

Lots

1

1 awarded

Published

22 Aug 2025

Deadline 07 Jul 2025

Description

St Osyth Priory & Parish Trust is currently in the development phase of a National Lottery Heritage Fund grant which will focus on the redevelopment of the Tithe Barn and Old Dairy and into hireable event and community spaces. St Osyth Priory and Parish Trust wishes to appoint a suitably qualified and highly experienced Multi Disciplinary Design Team to work on the Development and Delivery Phases - RIBA 2 to RIBA 7 of this aspect of the project. This ITT sets out the background to the project, the tender process, timescales, and management arrangements. There is, however, no guarantee that Delivery Phase services will be required, and bidders should take account of this. Below is an approximate timeline of the programme: RIBA Stage 2 - July 2025 - December 2025 1. Pre-planning Application Submitted - September 2025 to November 2025 2. Ongoing SOPPT Meetings RIBA Stage 3 - December 2025 - August 2026 1. Coordinated Designs & costs Approved - May 2026 2. Match Funding for Delivery Phased secured and in place, agreements in place - May 2026 to August 2026 3. Planning/LBC Applications - April 2026 - May 2026 4. Delivery Phase Application Prepared - June 2026 - July 2026 5. Delivery Phase Application Submitted - August 2026 6. Planning/LBC Decision - TBC 7. Ongoing SOPPT Meetings End of Development Phase RIBA Stage 4 - January 2027 to June 2027 1. Decision on Delivery Phase Application - December 2026 (TBC) 2. Estimated Permission to Start Received (Delivery Phase) - January 2027 3. Discharge Pre-Commencement Planning/LBC conditions - February 2027 to May 2027 4. Ongoing SOPPT Meetings RIBA Stage 5 - November 2027 to January 2029 1. Construction - December 2027 to October 2028 2. Fit out and interpretation installation period - November 2028 to January 2029 3. Ongoing SOPPT Meetings RIBA Stage 6 Handover of sites & testing for close out - January 2029 - March 2029 1. Ongoing SOPPT Meetings RIBA Stage 7 In use and open for Autumn - March 2029 - May 2029 1. Ongoing SOPPT Meetings 2. Project Evaluation Submitted - March 2029 to May 2029 3. Activity period and programme ends - May 2029 SOPPT will also be procuring or have procured the following Consultants to comprise the Project Team: • Project Manager • Quantity Surveyor • Multi-Disciplinary Design Team • Activity Plan, Community Consultation and Co-Production Consultant • Business Planner • Evaluation, Economic and Social impact Consultant • Fundraising Consultant • Others as required The current anticipated construction value is £2.908 million excluding VAT, inflation, contingency and fees. All applications, enquiries and requests for site visits need to be sent to tenders@stosythprioryandparishtrust.org What to include: - Case Studies - Details of who will be involved, including Bios and CVs - Community and Stakeholder Engagement - Methodology and Timeline - References - Insurance - Social value - Cost breakdown

Scope

Reference
St. Osyth Priory and Parish procurement 2
Total value
£227,359 excluding VAT
Commercial tool
Standalone contract
Contract dates
14 Jul 2025 to 30 Jan 2029
CPV classifications
71200000

Submission & procedure

Submission deadline
07 Jul 2025, 9:00 am

Award details

Awarded supplier(s), contract period and value as published in the award notice.

Awarded value

£138k

Award date

17 Aug 2025

Contract start

14 Jul 2025

Contract end

30 Jan 2029