Salford Crescent - Terracotta Cladding
Estimated value
£50k
Awarded value
£213k
Suppliers
0
Lots
1
Published
06 Jan 2026
Description
The planned construction of a third platform at Salford Crescent station aims to improve passenger flow and reduce train delays by allowing more flexibility for trains traveling through central Manchester and across the country. The construction project includes the addition of a new lift shaft and stairs from the existing ticket office. The scheme is part of a package of proposed measures in the Manchester area that are being designed/planned to boost capacity and resilience, emanating from the Cross Manchester Capacity and Reliability Improvement Study. Improving the operation of train services in the centre of Manchester and providing further capacity at Salford Crescent Station, it aligns with the strategic aims of Network Rail, TfGM, TfN and the wider industry. Kier are seeking expressions of interest for Terracotta cladding on the lift shaft at Salford Crescent.
Scope
- Reference
- C4A90483125
- Total value
- £50,000 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 16 May 2025 to 29 May 2025
- CPV classifications
- 45262650 44212381
Submission & procedure
- Submission deadline
- 24 Feb 2025, 5:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£213k
Award date
27 May 2025
Contract start
16 May 2025
Contract end
29 May 2025