HE0915 M4 Junction 17 Improvement Works
Estimated value
—
Awarded value
£21.6m
Suppliers
1
Lots
1
Published
26 Mar 2026
Description
Wiltshire Council are procuring a contract for the delivery of the M4 Junction 17 improvement works, with a view to awarding the contract in early spring 2026. Scope of Works The proposed scheme includes: • Installation of traffic signals on all roundabout approaches • Carriageway widening throughout the junction • Increasing the number of traffic lanes across the motorway bridges from two to three • Widening of the circulatory carriageway The successful contractor must be capable of working on the National Highways network and experienced in delivering complex highway infrastructure improvements. Delivery Phases (estimated) The contract will be delivered in two phases: • Phase 1 – Early Contractor Involvement (ECI): Spring 2026 – Autumn 2026 • Phase 2 – Construction: 2027 (subject to approval of the Full Business Case by the Department for Transport) Estimated Value • £27 million (including VAT)
Scope
- Reference
- HE0915
- Commercial tool
- Standalone contract
- Contract dates
- 05 Apr 2026 to 29 Sept 2028
- CPV classifications
- 4523310045233110
- Contract locations
- Wiltshire, United Kingdom
- Particular suitability
- Small and medium-sized enterprises (SME)
Award criteria
Criteria the buyer will use to evaluate bids.
| Name | Description | Type | Weighting |
|---|---|---|---|
| Quality | — | quality | 60.00% |
| Price | — | price | 40.00% |
Participation
Conditions suppliers must meet to bid.
Please refer to the tender documentation
Submission & procedure
- Procedure
- Open procedure
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£21.6m
Award date
26 Mar 2026
Contract start
26 Apr 2026
Contract end
27 Apr 2028