FRM School; Facilities programme; Main House contingencies; protective wind film install on single glazed windows.
Estimated value
£12k
Awarded value
£12k
Suppliers
1
Lots
1
Published
26 Jul 2023
Description
The Main House is predominately glazed with float glass that is comparatively weak that forms into sharp shards when it breaks. Many years ago a project had been completed to install a safety film to some of the risk glazing to upgrade the safety of the glass to meet the requirements of the Workplace Regulation 14. However the random tests found most of this film was very old or poor initial quality and had either degraded offering little base film strength or was failing through lack of adhesion to the glass. Both would be deemed as providing inadequate protection. The works required would pull the existing base film from the glass where installed, soften the residue adhesive and scrap from the glass, preclean the panes and install Saint Gobain 4MIL Safety Film to 133 second floor panes, 128 first floor panes, 348 ground floor panes and 148 basement panes In addition further similar works would also be completed on Philp House
Scope
- Reference
- tender_341965/1240417
- Total value
- £12,236 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 09 Jul 2023 to 24 Aug 2023
- CPV classifications
- 45421100
Submission & procedure
- Submission deadline
- 26 Jun 2023, 10:59 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£12k
Award date
09 Jul 2023
Contract start
09 Jul 2023
Contract end
24 Aug 2023