EcoSF4: NE Hub Eel Pass Improvement Programme, Development & Design
Estimated value
£57k
Awarded value
£57k
Suppliers
1
Lots
1
Published
16 Jul 2026
Description
Objectives The objective of the project is to on behalf of the Environment Agency (the Contracting Authority) complete an optioneering study for each of the three sites to identify the preferred option for eel passage. This should then be progressed to detailed design suitable for construction. The eel pass design at each site should deliver the following objectives: • To provide long term safe passage of eels past the structure, and operate reliably during eel and elver migration periods • To provide an eel passage solution that can be safely constructed, operated, maintained and decommissioned; • Is cost-effectivecost-effective to maintain, accessible for cleaning and inspections, and allows for monthly checks without specialist knowledge • To provide an eel pass solution that is robust enough to withstand the hydraulic conditions and debris experienced at each structure. • To provide consideration of whole life costs and whole life carbon to support decision making in the determination of the preferred option • To meet the requirements set out in LIT 75351 AM TA Eel Pass, Fish Pass and Fish Counters Maintenance Instruction and Guide. • Non powered solutions are preferred; however, the Environment Agency will consider more innovative solutions for Houghton Weir.
Scope
- Reference
- CF-0656600D8d000003VQwdEAG
- Total value
- £57,285.75 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 19 Jul 2026 to 18 Jul 2027
- CPV classifications
- 90700000
Submission & procedure
- Submission deadline
- 19 Jun 2026, 11:00 am
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£57k
Award date
15 Jul 2026
Contract start
19 Jul 2026
Contract end
18 Jul 2027
Awarded suppliers· 1 supplier
Awarded 15 Jul 2026 · Contract period 19 Jul 2026 — 18 Jul 2027
Other contracts from Environment Agency
Full notice and award history for this contracting authority is on the buyer profile.
Other contracts awarded to Fishtek Consulting· 10
Cross-buyer view of this supplier's public-sector wins.
| Title | Type | Value | Published |
|---|---|---|---|
| Pont Ends River Restoration: Detailed Design | contract | £53k | 28 Oct 2025 |
| Wilmslow Park Weir | contract | £79k | 12 Dec 2024 |
| Ecological Services Framework (EcoSF4) | contract | £1.4m | 07 Nov 2024 |
| Ecological Services Framework (EcoSF) 4 | contract | — | 07 Nov 2024 |
| EAN - ECOSF3 - Gressenhall Mill | contract | £26k | 27 Sept 2024 |
| NHDC 0723 River Oughton Collapsed Weir Detailed Design 2023 - AWARD | contract | £80k | 11 Sept 2023 |
| Derril Water WFD Improvements Project | contract | £21k | 19 Jul 2022 |
| NEA - EcoSF3 - Lot 4 - Eel Regulation Compliance - Feasibility Study | contract | £34k | 17 Nov 2021 |
| project_31023 - Manchester Ship Canal Fish Pass Feasibility Project | contract | £55k | 12 Jan 2021 |
| Proposed Removal of Keybridge Weir - Assessment & Project Development - Award | call off | £11k | 30 Sept 2020 |