Design and Build Pottery Terrace Rock Ramp Fish Easement
Estimated value
£65k
Awarded value
£50k
Suppliers
1
Lots
1
Published
10 Feb 2022
Description
The construction of a rock ramp type fish pass at Pottery Terrace Weir (PTW) on the River Douglas (Wigan), is part of the Opening Up the River Douglas programme (OUR Douglas), part funded by the European Regional Development Fund (ERDF) this project is below the thresholds for a full procurement procedure under the Public Contracts Regulations 2015. RRT is still under and obligation to ensure compliance with EU principles of transparency, equality and non-discrimination, as such RRT is conducting a formal tender process in which all bidders will be treated equally, with no discrimination and through a transparent process. The project aims to specifically address and improve fish passage in the Douglas Catchment, creating a fish easement which allows for the passage of all fish species at all times. This tender is for the Detailed design and Construction of a rock ramp type fish pass at Pottery Terrace Weir on the river Douglas, Wigan. To apply visit https://ribbletrust.org.uk/our-douglas-contract-opportunity-6/
Scope
- Reference
- OURD-07
- Total value
- £65,293 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 18 Jul 2021 to 29 Sept 2022
- CPV classifications
- 45240000
- Particular suitability
- Small and medium-sized enterprises (SME)
Submission & procedure
- Submission deadline
- 24 Jun 2021, 4:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£50k
Award date
01 Feb 2022
Contract start
18 Jul 2021
Contract end
29 Sept 2022