20-182 Rotherham Renaissance Flood Alleviation Scheme Phase 2C (RRFAS2C): Ground Investigation for Canal Barrier

Rotherham MBCcontractContracts FinderRef ROTHMBC001-DN490176-49055687SME suitableVCSE suitablecomplete
View buyer

Estimated value

£50k

Awarded value

£47k

Awarded 12 Sept 2020

Suppliers

1

Lots

1

1 awarded

Published

14 Sept 2020

Deadline 26 Aug 2020

Description

The scope of works required for this procurement include all: • Pre-commencement planning • Landowner/stakeholder liaison • Site operations • Monitoring • Factual reporting preparation and submission in connection with the Rotherham Renaissance Flood Alleviation Scheme 2C (RRFAS2C) Canal Barrier Ground Investigation, as set out within the Tender Documentation The scheduled works within the navigable canal and its towpaths (the canal environment) must be undertaken during a 'winter stoppage' of the canal that has already been booked/agreed between the Canal & River Trust and Rotherham MBC. The stoppage period is from 2nd November 2020 to 11 December 2020. Rotherham MBC would incur penalties of £10,000 per day if ground investigations works overrun beyond 11th December 2020 and therefore its expectation is that the ground investigation within the canal environment will be planned to be completed in the first 3 weeks of the above stoppage period to ensure a substantial contingency is allowed for in the programme. Scheduled works outside of the canal environment (as defined above) can be undertaken outside of the above stoppage period.

Scope

Reference
ROTHMBC001-DN490176-49055687
Total value
£50,000 excluding VAT
Commercial tool
Standalone contract
Contract dates
13 Sept 2020 to 11 Dec 2020
CPV classifications
71351500
Particular suitability
Small and medium-sized enterprises (SME)Voluntary, community and social enterprises (VCSE)

Submission & procedure

Submission deadline
26 Aug 2020, 11:00 am

Award details

Awarded supplier(s), contract period and value as published in the award notice.

Awarded value

£47k

Award date

12 Sept 2020

Contract start

13 Sept 2020

Contract end

11 Dec 2020