Pendle Phase 2 Construction
Estimated value
£27.6m
Awarded value
£27.6m
Suppliers
1
Lots
1
Published
09 Oct 2024
Description
Willmott Dixon Construction Limited were appointed in October 2023, via a twostage design and build tender, to design Pendle Police Station to the end of RIBA Stage 4, plus carry out early works to secure planning permission. The design was completed and approved in March 2024. A fixed price tender of £25.6m has been submitted for construction works. Other costs, such as commissioning and risk costs, have also been revalidated at the end of RIBA Stage 4 at a total cost of £2m bringing the total cost for the construction element of the project to £27.6m.
Scope
- Reference
- In-Tend 2260
- Total value
- £27,600,000 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 18 Jul 2024 to 15 Dec 2025
- CPV classifications
- 45000000
Submission & procedure
- Submission deadline
- 10 Jul 2024, 11:00 am
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£27.6m
Award date
09 Jul 2024
Contract start
18 Jul 2024
Contract end
15 Dec 2025