Provision of Architects to support the Estates Improvement Programme for the University of Sunderland - AWARD

University of SunderlandcontractContracts FinderRef UOS/Architects EIRP/0919 - AWARDcomplete
View buyer

Estimated value

Awarded value

£373k

Awarded 19 Dec 2019

Suppliers

1

Lots

1

1 awarded

Published

19 Dec 2019

Deadline 29 Nov 2019

Description

Specification for Authority The University are looking to appoint an Architect to act as lead designer for the proposed Estates Rationalisation Programme working alongside the University's externally appointed Programme Manager. This 3 to 5-year programme consists of a series of inter-related projects across the University estate to be undertaken with the aim of improving estate suitability, condition, space utilisation and cost efficiency. The Programme is in its early phase of development with planning for Summer 2020 now underway. The first phase of the programme will involve the following projects: o Relocation of photography from St Mary's Buildings, City Campus to Level 2 of the David Goldman building at the St Peter's Campus; o Relocation of CEG from Johnson building, City Campus to Reg Vardy, Level 3, St. St. Peters Campus and to repurpose the existing Johnson building footprint into staff/student parking; o Refurbishment of David Goldman, ground floor area, St Peters Campus (works include EUZ and LEP funding required to be spent by January 2021); o Relocation of Estates & Facilities and Enterprise & Innovation Services from Design Centre building, into St. Marys Building, both buildings are on the City Campus; o Relocation of Print Centre out of Design Centre building, City Campus off Campus (with potential retention of small outlets on campus); o Demolition of the Design Centre building, City Campus. The above identifies the required projects for phase 1 of this ambitious programme, projects may be added or removed from the programme as it is developed. Phase 1 of the works are to be completed by August 2020 with the demolition works noted above to be completed by December 2020. The successful architect will be expected to act within a lead designer capacity on all projects within Phase 1 of the overarching programme; it is unlikely, at this stage, that a single design team will be appointed for the entire Estate Rationalisation programme. It is expected the architect will be involved in delivery from inception to post completion activities for works associated with Phase 1. The architect will be expected to report ultimately to the Programme Manager; Extensive liaison with client Faculty and Service colleagues will be required under this commission within the stewardship of the Programme Manager and / or the individual Project Manager(s), working alongside the Estates Development Manager including the Deputy Director of Estate & Facilities. Please note, expressions of interest outside the University framework reference: UoS/Architects QS/1117 will not be accepted and will be removed without further correspondence.

Scope

Reference
UOS/Architects EIRP/0919 - AWARD
Commercial tool
Standalone contract
Contract dates
16 Dec 2019 to 15 Dec 2020
CPV classifications
71000000

Submission & procedure

Submission deadline
29 Nov 2019, 12:00 am

Award details

Awarded supplier(s), contract period and value as published in the award notice.

Awarded value

£373k

Award date

19 Dec 2019

Contract start

16 Dec 2019

Contract end

15 Dec 2020

Awarded to