Refurbishment of Block 21, Alderley Park, to accommodate the Lighthouse laboratory.
Estimated value
£900k
Awarded value
£900k
Suppliers
1
Lots
1
Published
28 May 2020
Description
Refurbishment of Block 21, Alderley Park, to accommodate the Lighthouse laboratory. The Lighthouse laboratory is based at Alderley Park science park. Alderley Park is owned by Bruntwood. As a result, any refurbishment of the premises at Alderley Park, in order to accommodate the Lighthouse laboratory, were undertaken by Bruntwood. In its response to COVID-19 and with only days available, MDC, on behalf of the Department of Health and Social Care, is entering into contracts without competition or advertising the requirement. In accordance with the Public Contracts Regulations (2015) and Procurement Policy Note 01/20, the following tests have been met: • There are genuine reasons for extreme urgency - the response to the COVID-19 consequences needs to be immediate because of public health risks. • The events that have led to the need for extreme urgency were unforeseen - the COVID-19 situation is so novel that the consequences are not something that MDC could have predicted. • It is impossible to comply with the usual timescales in the Public Contract Regulations (2015) - there is no time to run an accelerated procurement under the open or restricted procedures or competitive procedures with negotiation, nor does the MDC have access to an existing commercial agreement such as a framework or dynamic purchasing system. The situation is not attributable to the MDC - MDC has not done anything to cause or contribute to the need for extreme urgency.
Scope
- Reference
- MEDDISC001-DN480136-69335199
- Total value
- £900,000 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 07 Apr 2020 to 29 Jun 2020
- CPV classifications
- 45000000
Submission & procedure
- Submission deadline
- 01 Apr 2020, 11:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£900k
Award date
06 Apr 2020
Contract start
07 Apr 2020
Contract end
29 Jun 2020