CP1680-18 A382 Corridor Improvements Phase 1
Estimated value
£7.0m
Awarded value
£4.7m
Suppliers
1
Lots
1
Published
28 Apr 2020
Description
The A382 corridor improvement phase 1 is a highways construction scheme to widen and level the existing A382 carriageway from Forches Cross to Whitehills Cross, Newton Abbot. The scheme will see the carriageway widened to 10m and pedestrian/cycle facilities installed. The procurement documents are available for unrestricted and full direct access, free of charge, at: http://www.supplyingthesouthwest.org.uk Tenders or requests to participate must be submitted electronically via: http://www.supplyingthesouthwest.org.uk. Time limit for receipt of tenders or requests to participate: Date: 19/07/2019 Local time: 12:00
Scope
- Reference
- DVNCC001-DN387923-71134034
- Total value
- £7,000,000 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 23 Sept 2019 to 30 Jul 2020
- CPV classifications
- 45000000
Submission & procedure
- Submission deadline
- 18 Jul 2019, 11:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£4.7m
Award date
06 Dec 2019
Contract start
23 Sept 2019
Contract end
30 Jul 2020