Havant Thicket Reservoir Project - Main Reservoir Works (MRW+)
Estimated value
£88.4m
Awarded value
—
Suppliers
0
Lots
1
Published
04 Jan 2021
Description
This represents a flagship project to construct the first new strategic water resource, and corresponding pipeline, in the South East for decades. Construction work is anticipated to start on the Havant Thicket Reservoir Project (the "Project") in 2024, for completion by 2029. The Project is socially, economically and environmentally significant. It is the product of collaborative regional water planning particularly between Portsmouth Water and Southern Water, and forms a key step in increasing water resilience in the South East. This Contract Notice relates to the appointment of the main works contractor for main reservoir works and additional elements ("Main Reservoir Works (MRW+) Contract" or the "Contract"), as further described at Section II.2.4). The main works pipeline contract and framework agreement under the Project are the subject of a separate contract notice being published at or around the same time as this Contract Notice.
Scope
- Reference
- ocds-h6vhtk-02878d
- Total value
- £88,400,000 excluding VAT
- Commercial tool
- Standalone contract
- Main category
- works
- CPV classifications
- 450000004510000045111200451112404511200045112200451124004511250045112600451130004521231245252120452521267130000071310000713110007131130071322000713224007133400071530000715400007154100071631460
- Contract locations
- Portsmouth
Submission & procedure
- Submission deadline
- 15 Feb 2021, 12:00 pm
- Submission address
- https://portsmouthwater.app.jaggaer.com/go/334489850175DB21B68F ↗
- Procedure
- Negotiated procedure with prior call for competition