Salford Crescent - Accommodation Block
Estimated value
£25k
Awarded value
£107k
Suppliers
0
Lots
1
Published
05 Jan 2026
Description
The planned introduction of construction of a third passenger platform with new lift and stairs from existing ticket office, including signalling works, SME works, new mess facility, new ticket line. This was discovered by Network Rail in there plan to develop stations like Salford Crescent to improve value of life within transport. Therefore, in response Network Rail have set out to start this improvement of Salford Crescent by upgrading the station with the listed above. The scheme is part of a package of proposed measures to improve the situations of current stations like Salford Crescent to help boost capacity and flow within the surrounding areas. This lies with one of many projects within the Manchester area that are set to be upgraded. A remodelling of the station at Salford Crescent, specifically a platform addition will be essential to accommodate the planned implementation of longer rolling stock services. Kier are seeking expressions of interest for early contractor engagement in relation to the Accommodation block. The package will consist of construction and fit out works, including brickwork, internal fit out, fitting and decorations and window installations at Salford Crescent, specifications to be confirmed. This will be the first official IDC/IDR to enable the progression of the first few design packages required for us to start on site in September 2025.
Scope
- Reference
- C4A90753042
- Total value
- £25,000 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 31 Jul 2025 to 20 Nov 2025
- CPV classifications
- 45213320 45210000 45212413 45213321
Submission & procedure
- Submission deadline
- 28 Feb 2025, 5:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£107k
Award date
26 Aug 2025
Contract start
31 Jul 2025
Contract end
20 Nov 2025