Schools M&E Packages - Schools Capital Programme 2019
Estimated value
£250k
Awarded value
£1.0m
Suppliers
1
Lots
1
Published
09 Aug 2019
Description
The Authority is seeking Tender submissions for three lots of M&E works across seven schools. This procurement has been divided into lots, as below: Lot 1: • Broadgreen Primary - Hot and cold water replacement • Smithdown Primary - Phase 2 heating replacement • Windsor Primary School - New Boiler Plant and Phase 1 Heating replacement Lot 2: • 2.1 Norman Pannell School - New Boiler Plant and Phase 1 Heating replacement • 2.2 Woolton Primary School -New Boiler Plant and Phase 1 Heating replacement Lot 3: • 3.1 Booker Ave Junior School - New boiler Plant & Heating pipework • 3.2 Sudley Infants - New Boiler Plant & Heating pipework distribution All Lots will be awarded separately. Bidders can bid on all Lots.
Scope
- Reference
- LPOOL001-DN401495-27948689
- Total value
- £250,000 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 21 Jul 2019 to 31 Aug 2019
- CPV classifications
- 50000000
- Particular suitability
- Small and medium-sized enterprises (SME)Voluntary, community and social enterprises (VCSE)
Submission & procedure
- Submission deadline
- 02 May 2019, 11:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£1.0m
Award date
20 Jun 2019
Contract start
21 Jul 2019
Contract end
31 Aug 2019