GB-Shaftesbury: Plantroom No 2, Replacement Hot Water Service Plant, Westminster Memorial Hospital, Shaftesbury.
Estimated value
—
Awarded value
—
Suppliers
1
Lots
1
Published
02 Mar 2016
Description
Strip-out of the existing boilerplant with the boiler flues, LPHW services, local gassupplies and electrical services in 2 stages as the hot water service plant is replaced whilst one of the existing boilers continues to provide the heat source for the HWS. Installation of the first new hot water generator with its flue and local gas, cold feed and HWS F&R pipework connections Installation of a new plant control panel and electrical services from the new control panel to the first hot water generator, its HWS destratification pump, the new HWSreturn circulation pump and the new gas safety valve. Commissioning of the first new hot water generator. Please refer to specification for full description of works.
Scope
- Reference
- BIP193253794
- Commercial tool
- Standalone contract
- Contract dates
- 23 Feb 2016 to 29 Mar 2016
- CPV classifications
- 71334000 45215000 45331000 42164000 45310000 45351000
Submission & procedure
- Submission deadline
- 22 Feb 2016, 12:00 am
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
—
Award date
22 Feb 2016
Contract start
23 Feb 2016
Contract end
29 Mar 2016