Structural Groundworks and site modifications
Estimated value
£250k
Awarded value
£723k
Suppliers
1
Lots
1
Published
16 Jan 2025
Description
Penzance Dry Dock (PDD) is famously steeped in history, currently being the oldest operational dry dock of its type in Europe but requires drastic investment after decades of neglect and dilapidations. While the surrounding shipyards, across the county and country have seen investment, PDD has slipped through the net time and time again. PDD plans to complete a large refit by March 2025. PDD will become the engineering powerhouse that it once was, but with more abilities than ever before. This facility has primally been ship repair only, but now we are supporting multiple areas of the market, ship repair, ship building, mass fabrication and most importantly training and skill development. This capital investment, part-funded by the UK Government through the UK Shared Prosperity Fund, will see the site brought up to an even playing field with the rest of industry, with new, safer lifting systems and the dilapidations being rectified. We will see our efficiency drastically increased which in turn will assist in reducing our carbon footprint. We are seeking a supplier to complete the structural groundworks and site modifications as detailed in the specification and supporting documents.
Scope
- Reference
- BUS003_0081_1.6
- Total value
- £250,000 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 22 Nov 2024 to 14 Feb 2025
- CPV classifications
- 44114000 44212400 45000000
- Particular suitability
- Small and medium-sized enterprises (SME)
Submission & procedure
- Submission deadline
- 08 Nov 2024, 5:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£723k
Award date
22 Nov 2024
Contract start
22 Nov 2024
Contract end
14 Feb 2025