HCC - 05/19 - The Construction of a 77 Bed/Care/Nursing Home and Associated Works at the former Wormley School, St Laurence Drive, Wormley, Hertfordshire - AWARD
Estimated value
£12.5m
Awarded value
£12.5m
Suppliers
1
Lots
1
Published
03 Mar 2020
Description
Following a procurement, Hertfordshire County Council has awarded contracts for the Provision of a 77 Bed/Care/Nursing Home and Associated Works at the former Wormley School in Hertfordshire This is an award notice and this opportunity is now closed. The successful supplier is Clegg Construction Ltd The estimated total value of the Contract is £12,500,000.00 and is for the core Contract period. The initial term of this contract is between 72 - 80 week build OJEU Contract Notice Number: 2019/S 096-231101 OJEU Award Notice Number: 2019/S 235-574974
Scope
- Reference
- HCC1911274 - AWARD
- Total value
- £12,500,000 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 01 Nov 2019 to 30 May 2021
- CPV classifications
- 45000000 45210000 45215000
- Particular suitability
- Small and medium-sized enterprises (SME)
Submission & procedure
- Submission deadline
- 16 Jun 2019, 11:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£12.5m
Award date
18 Nov 2019
Contract start
01 Nov 2019
Contract end
30 May 2021
Awarded suppliers· 1 supplier
Awarded 18 Nov 2019 · Contract period 01 Nov 2019 — 30 May 2021
Other contracts from Supply Hertfordshire
Full notice and award history for this contracting authority is on the buyer profile.
Other contracts awarded to Clegg Construction Limited· 10
Cross-buyer view of this supplier's public-sector wins.
| Title | Type | Value | Published |
|---|---|---|---|
| PAN3230 - Stocking Farm Housing Scheme | contract | £18.8m | 24 Jun 2026 |
| PAN3230 - Stocking Farm Housing Scheme | contract | — | 24 Jun 2026 |
| George Street Hotel Development | contract | £425k | 07 Oct 2025 |
| Housing 21 - The Griffin Extra Care | contract | £22.0m | 22 May 2025 |
| 4184.EFM.SW.24 Faculty of Health Phase 1 New Build | call off | £15.7m | 31 Jan 2025 |
| 4184.EFM.SW.24 Faculty of Health Phase 1 New Build | contract | — | 31 Jan 2025 |
| Chesterfield Road Redevelopment | contract | — | 24 Jan 2025 |
| COV - Woodlands Redevelopment - Main Contractor - AWARD | contract | £22.4m | 22 May 2024 |
| Scape Regional Construction Framework | contract | — | 08 Sept 2022 |
| Scape Regional Construction Framework. | call off | £98.2m | 29 Apr 2021 |