A417 Missing Link - Sheet Piling

KIER TRANSPORTATION LIMITEDcontractContracts FinderRef A417 Missing Link - Sheet Pilingcomplete

Estimated value

£240k

Awarded value

£241k

Awarded 20 Dec 2024

Suppliers

1

Lots

1

1 awarded

Published

29 Oct 2025

Deadline 27 Sept 2024

Description

Purpose of Notice - The procurement of a Subcontractor for the Sheet Piling works associated with Grove Farm in connection with the A417 Missing Link at Air Balloon. Scheme Description - Under the National Highways Limited Regional Delivery Partnership (RDP), we are appointed as the Principal Contractor for the design and construction of a new dual carriageway at the A417 Missing Link at Air Balloon. The scheme would provide 3.4 miles (5.5km) of new, rural all-purpose dual carriageway for the A417. The new dual carriageway would connect the existing A417 Brockworth bypass with the existing dual carriageway A417 south of Cowley. Registering Interest - Interested parties are to register their interest through making contact via guy.hornsey@kier.co.uk.

Scope

Reference
A417 Missing Link - Sheet Piling
Total value
£240,000 excluding VAT
Commercial tool
Standalone contract
Contract dates
03 Feb 2025 to 26 Feb 2027
CPV classifications
45000000

Submission & procedure

Submission deadline
27 Sept 2024, 4:00 pm

Award details

Awarded supplier(s), contract period and value as published in the award notice.

Awarded value

£241k

Award date

20 Dec 2024

Contract start

03 Feb 2025

Contract end

26 Feb 2027