GB-Swindon: UKRI-3443 Battery Energy Storage System for the ASPIRE-II Project

UK Research & InnovationcontractContracts FinderRef BIP869429329complete

Estimated value

£111k

Awarded value

£111k

Awarded 28 May 2024

Suppliers

1

Lots

1

1 awarded

Published

18 Jun 2024

Deadline 28 May 2024

Description

The ASPIRE II project aims to create an Ammonia Synthesis Plant powered solely by renewable energy. It aims to prove the plant's reliability in off-grid settings with varying climates. Featuring four main subsystems and the capability to adjust ammonia production based on available renewable power, the Battery Energy Storage System (BESS) seeks to manage fluctuations between plant consumption and variable renewable energy sources.

Scope

Reference
BIP869429329
Total value
£111,279 excluding VAT
Commercial tool
Standalone contract
Contract dates
29 May 2024 to 07 Oct 2024
CPV classifications
31440000

Submission & procedure

Submission deadline
28 May 2024, 11:00 pm

Award details

Awarded supplier(s), contract period and value as published in the award notice.

Awarded value

£111k

Award date

28 May 2024

Contract start

29 May 2024

Contract end

07 Oct 2024