Scaled Mooring Line Test Rig Design

Offshore Renewable Energy CatapultcontractContracts FinderRef OREC001-DN651648-88823259SME suitablecomplete
View buyer

Estimated value

£150k

Awarded value

£150k

Awarded 08 Mar 2023

Suppliers

1

Lots

1

1 awarded

Published

16 Mar 2023

Deadline 16 Feb 2023

Description

ORE Catapult is currently developing a technology test and development facility in Aberdeen, known as FLOWIC (Floating Offshore Wind Innovation Centre). As part of the development of this Centre, ORE Catapult is scoping the design, and in certain cases manufacture, of a suite of testing rigs. Within FLOWIC, there is a desire to have capability that can support the development of mooring components for floating offshore wind. Mooring components include, amongst others: Synthetic Fibre Rope, Chain, Steel Spiral rope, and associated linkages. The primary loading mechanism of these components is pure tension, and these components often have very high breaking loads (circa 10,000kN or more). As such, fundamental product development or research is often done on a 'sub-component' level at lower loads and sizes. To support the development of technology in this fashion, ORE Catapult wishes to commission a detailed design activity for the 'Scaled Mooring Line Test Rig' (SMLTR),

Scope

Reference
OREC001-DN651648-88823259
Total value
£150,000 excluding VAT
Commercial tool
Standalone contract
Contract dates
13 Mar 2023 to 30 May 2023
CPV classifications
71320000 79415200
Particular suitability
Small and medium-sized enterprises (SME)

Submission & procedure

Submission deadline
16 Feb 2023, 11:59 pm

Award details

Awarded supplier(s), contract period and value as published in the award notice.

Awarded value

£150k

Award date

08 Mar 2023

Contract start

13 Mar 2023

Contract end

30 May 2023

Awarded to