GB-Lincoln: The Bridge (Research and Development) Building
Estimated value
£3.1m
Awarded value
£3.1m
Suppliers
1
Lots
1
Published
05 May 2021
Description
This is a contract award notice for the main contractor for the construction of the University of Lincoln's Advanced Engineering and Research Development Building (Bridge R&D). The contractor is required to undertake RIBA stages 5-7. The Bridge R&D building is designed to be a collaborative research facility acting as a bridge between industry partners and the University. The facility, situated adjacent to the Lincoln Science and Innovation Park, will include a series of laboratory spaces housing specialist equipment such as a Transmission Electron Microscope and all spaces purpose built to reduce interference with external factors to the equipment within the building. The laboratory spaces include the following: 1. Electron Microscopy Lab 2. Clean Room (ISO Class 6) 3. Wet Lab 4. Dry Lab 5. Materials Lab At approx. 750sqm, the design of the building has been completed to RIBA Stage 4. The scheme is externally funded by the European Regional Development Fund along with the Greater Lincolnshire Local Enterprise Partnership via the Single Local Growth Fund. The scheme is required to achieve BREEAM Excellent and is currently on target to achieve this. Full planning permissions for the scheme has been received. The University has conducted a below OJEU two stage procedure including a Shortlisting Questionnaire, followed by a second tender stage for the shortlisted contractors.
Scope
- Reference
- BIP581947896
- Total value
- £3,077,982.68 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 25 Apr 2021 to 10 Apr 2022
- CPV classifications
- 45210000
Submission & procedure
- Submission deadline
- 19 Mar 2021, 12:00 am
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£3.1m
Award date
19 Mar 2021
Contract start
25 Apr 2021
Contract end
10 Apr 2022