The works comprise the replacement of three existing 11 kV Paper Insulated Lead Covered (PILC) feeder cables supplying Guy’s Hospital, which are exhibiting insulation oil leakage and present a risk of circuit failure. The project will install new 240 mm² BS 7835 11 kV LSZH XLPE single‑core AWA cables, installed in trefoil formation on new heavy‑duty galvanised steel cable ladder systems with appropriately rated trefoil cleats. The new cable routes traverse internal plantrooms, service ducts, service tunnels, ceiling voids and external roof areas. Works within service ducts and tunnels require confined‑space trained operatives and a dedicated rescue team.
Scope
- Reference
- C397709
- Commercial tool
- Standalone contract
Submission & procedure
- Procedure
- Below threshold - limited competition
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
—
Award date
—
Contract start
—
Contract end
—
Awarded suppliers· 1 supplier
Awarded —
Other contracts from Guy's and St Thomas' NHS Foundation Trust
Full notice and award history for this contracting authority is on the buyer profile.
Other contracts awarded to Playfords Limited· 10
Cross-buyer view of this supplier's public-sector wins.
| Title | Type | Value | Published |
|---|---|---|---|
| WLT - St Bernard's LV2 Substation Upgrade | contract | — | 12 Mar 2026 |
| Secure Area Refurbishment Works | contract | — | 14 Jan 2026 |
| Small Works Framework - Lot 4 | contract | — | 01 Sept 2025 |
| CA14925 - 5295:18 - RFL Provision of Generator Replacement Project | contract | £19.5m | 14 Mar 2025 |
| Wireless Access Points & Associated Brackets | contract | £80k | 27 Nov 2023 |
| ST23-P060 DSEC: Design, Supply, Installation, Testing and Comm of the Generator | contract | £509k | 13 Nov 2023 |
| WHTHT - AAU Substation High and Low Voltage Upgrades | contract | £900k | 29 Mar 2023 |
| PAHT - HV Switchroom Works | contract | £561k | 22 Feb 2023 |
| CA9637 - PR7653 - The Provision of G-East and CSB Plantroom Works | contract | £677k | 15 Nov 2022 |
| Installation of data cabling | contract | £35k | 12 Jul 2022 |