Robotics and Autonomous Systems ("R&AS") Command and Control Centre
Estimated value
£1.0m
Awarded value
£1.6m
Suppliers
1
Lots
1
Published
05 Jan 2022
Description
ORE Catapult (https://ore.catapult.org.uk) is the UK's leading technology innovation and research centre for offshore renewable energy. ORE Catapult's vision is to be the world's leading offshore renewable energy technology centre by 2030. ORE Catapult will play a key role in delivering the UK's largest clean growth opportunity, through our mission to accelerate the creation and growth of UK companies in the offshore renewable energy sector. We will use our unique facilities and research and engineering capabilities to bring together industry and academia and drive innovation in renewable energy. ORE Catapult is now enhancing their capabilities further by developing a Robotics and Autonomous Systems (R&AS) facility to support the standardisation and compatibility of robot platforms across the offshore wind industry. ORE Catapult's new facilities will offer a range of test environments, including, but not limited to offshore testing, onsite testing, and demonstration zones. The site will offer an end-to-end process from prototype trials to post qualification field trials on operational assets. The construction of the building and development of the surrounding facilities is being funded by the North East Local Enterprise Partnership (NELEP) as part of the government's "Getting Building Fund". The Getting Building Fund forms part of the government's New Deal for Britain and sets out government's strategy to rebuild Britain and fuel economic recovery across the UK. As a result, the funding for the £1 million construction is time limited. The new facility has been designed to minimise our carbon footprint, utilising sustainable features in keeping with our renewable energy ethos. The construction design is being progressed to RIBA Stage 4 with Planning Permission being sought in parallel to the tender process. All relevant and appropriate surveys are also being conducted during this time. Due to the time limitations for the funding, it is critical that spend and construction is completed by March 2022 at our facility at Albert Street, Blyth, Northumbria, NE24 1LZ
Scope
- Reference
- OREC001-DN541149-60272527
- Total value
- £1,000,000 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 29 Sept 2021 to 30 Mar 2022
- CPV classifications
- 45000000
- Particular suitability
- Small and medium-sized enterprises (SME)
Submission & procedure
- Submission deadline
- 16 Jun 2021, 11:00 am
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£1.6m
Award date
21 Dec 2021
Contract start
29 Sept 2021
Contract end
30 Mar 2022