SC22323 - North Farm Gas Extraction System Replacement Works
Estimated value
£150k
Awarded value
£198k
Awarded 31 Jan 2023
Suppliers
1
Lots
1
1 awarded
Published
09 Feb 2023
Deadline 13 Jan 2023
Description
The primary work objective is to maintain or improve the gas infrastructure system to enable continued efficient operation of the existing gas flare, with the potential for future electricity generation through a gas engine. This objective will be met through construction of a replacement gas infrastructure network. For more information on the requirement please visit https://www.kentbusinessportal.org.uk/
Scope
- Reference
- KENT001-DN646004-56480593
- Total value
- £150,000 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 25 Feb 2023 to 20 Apr 2023
- CPV classifications
- 45000000
- Particular suitability
- Small and medium-sized enterprises (SME)
Submission & procedure
- Submission deadline
- 13 Jan 2023, 12:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£198k
Award date
31 Jan 2023
Contract start
25 Feb 2023
Contract end
20 Apr 2023
Awarded to