A645 Hensall R&R
Estimated value
£800k
Awarded value
£779k
Suppliers
1
Lots
1
Published
03 Jan 2020
Description
Section to plane 110mm deep and reinstate with 60mm deep binder course and 50mm surfacing. Sections to plane to 50mm deep and reinstate with 50mm surface course, a further 100mm deep to plane out in one area and reinstate with recycled material. Section to plane to 200mm deep and reinstate with 150mm deep recycled material and 50mm surfacing. Section to plane 40mm deep and reinstate with 40mm surfacing. Two sections of footway to plane 70mm deep with further 150mm deep excavation, reinstate footway. Kerb line to adjust, replacing any damaged. Spot damaged channels to replace. Road markings to be refreshed, existing drainage to be jetted and ironworks to adjust. Section of drainage work to do from under rail bridge.
Scope
- Reference
- NYCC001-DN377530-67835652
- Total value
- £800,000 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 11 Mar 2019 to 09 May 2019
- CPV classifications
- 45000000
- Particular suitability
- Small and medium-sized enterprises (SME)
Submission & procedure
- Submission deadline
- 08 Feb 2019, 12:00 am
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£779k
Award date
12 Feb 2019
Contract start
11 Mar 2019
Contract end
09 May 2019