G5-2E_HCC_041 Southampton TCF - A27 Providence Hill Cycle Link
Estimated value
£1.9m
Awarded value
£1.9m
Suppliers
1
Lots
1
Published
18 Jul 2025
Description
A call-off from Lot 2 (East) of the Generation 5 Civil Engineering, Highways & Transportation Collaborative Framework 2024 - 2028 (award notice published 01 February 2024). The S-TCF - Providence Hill Cycle Link scheme is to provide a new cycle link, combining both enhanced shared-use facilities and an on-carriageway bidirectional segregated cycle lane, on an approximately 820m stretch of the A27 between its junctions with Portsmouth Road and Church Lane it includes: - • New signal-controlled crossing at Portsmouth Road junction • New signal-controlled crossing at Blundell Lane junction • The on-carriageway bidirectional cycle lane shall be segregated with Cycle Lane Defenders • Priority crossings across Windmill Lane, Long Lane, Yachtsman's Close and Long Lane junctions • Carriageway inlay, new kerbing and footway, signing and lining • New street lighting
Scope
- Reference
- UN25825
- Total value
- £1,927,498.95 excluding VAT
- Commercial tool
- Standalone contract
- Contract dates
- 16 Dec 2024 to 07 Nov 2025
- CPV classifications
- 45230000
Submission & procedure
- Submission deadline
- 25 Nov 2024, 2:00 pm
Award details
Awarded supplier(s), contract period and value as published in the award notice.
Awarded value
£1.9m
Award date
29 Nov 2024
Contract start
16 Dec 2024
Contract end
07 Nov 2025